COURTYARD URBANIST · BRONZEVILLE · 9 OCTOBER 2026

4200 S. Indiana

Two-pass architectural and development review

Useful for concept discussion. Full room plans, independent egress, accessibility, survey, pricing and approvals remain open. This review does not make the project permit-ready or financially feasible.

Current starting scenario

Homes35
Total development cost$13,624,455
Study NOI DSCR0.85×
1.20× study cost gap$3,949,593
Cost reduction required29%
Enclosed cost target$186/sf

Illustrative rents, $275/gross-sf enclosed construction, 65% loan-to-cost, 6.5% interest, 30-year amortization and 5.5% cap rate. Apartment areas are gross; no bay area or architectural-detail premium is priced.

Implemented in this pass

Site-specific priorities

  1. Retain the strongest fit

    A/B each have 52.5 ft of street frontage; D has 50 ft. C uses equal 50-ft corner legs before the chamfer: straight street runs approximately 35.86 + 35.86 ft, with a separate 20-ft chamfer. Street bars are 40 ft deep; the inward wing is 30 ft wide.

  2. Resolve shared stairs before subdivision

    Four fronts currently use two shared stair/entry pairs. Make A/B and C/D identities clear, but obtain a fire-separation and exit-independence strategy before marketing them as separately commissionable buildings.

  3. Protect the ground-floor income

    Eight ground homes drive material income. Fit the slab-on-grade accessible routes, entrance vestibules and service rooms first; an excluded-ground sensitivity shows how much underwriting depends on them.

  4. Preserve light and the courtyard

    Coverage is about 60.6%, above the earlier 50% design aim. Compare a shorter south wing and a lighter courtyard-facing facade against lost rentable area; do not claim the existing count can be retained automatically.

Development tests

Each case starts from the same baseline. Cost targets are investigation thresholds, not contractor savings. “Remaining cost gap” retains the existing 1.20× NOI coverage, cash flow and value-at-cost checks.

ScenarioHomesDSCRRemaining cost gap
Construction −10%Enclosed construction rate only; bid target, not assumed savings.350.94×$2,731,673
Construction −20%Enclosed construction rate only; all other inputs held fixed.351.04×$1,513,753
Market rents +10%Sensitivity only; needs comparables. Affordable rents stay fixed.350.97×$2,635,429
Cost −15% + market rents +10%Combined test, not a forecast or contractor quote.351.12×$808,549
No ground-floor rentGround homes excluded; baseline construction cost retained. This measures income at risk.270.62×$6,577,988
10% affordable-home testRounded up to whole homes using existing placeholder rents; mix and City terms unverified.350.85×$3,949,593

Separate lender screen

At 1.25× coverage of cash flow after replacement reserves and an 80% LTV ceiling, supported debt is $5,907,908. Additional equity or confirmed funding versus the present loan assumption is $2,947,987. This addresses debt sizing; it does not erase the cost-over-value gap or establish an investor return. It is a stabilized-property comparison, not a construction financing commitment.

Second-pass scrutiny across all sites

  1. Room plans

    Complete one repeatable ground and upper dwelling type per entrance group before increasing counts. Trace every home entry through a coat vestibule; bedrooms and the office must open from a real hall/recess. Fit the primary ensuite, smaller bedrooms, required bath count and usable courtyard-facing island kitchen/dining. The model verifies gross allowances, not these room relationships.

  2. Egress and accessibility

    Verify independent exits, travel distances, enclosure/fire compartments, stair landings, clear door swings, accessible ground routes and grades. A drawn door is a location reservation; it does not certify a clear opening or a usable accessible route.

  3. Structure and envelope

    Ask a contractor to price a simple repeated structural/wet-stack grid first. Price bays, limestone, terracotta, quoins, cornices and gallery guards as separate alternates. Keep memorable detail at the entrances and corners while repeating ordinary windows and wall panels.

  4. Courtyard operations

    Keep sandbox and picnic tables visible from homes; maintain clear routes to all doors, refuse and alley. Develop drainage, winter maintenance, play surfacing, roots, soil volume and lighting. Furnishing footprints are checked against buildings; accessible maneuvering and continuous finished routes are not yet certified.

  5. Affordability and financing

    Underwrite the RFP affordability obligation and approved rent/utility schedule. Confirm construction-to-permanent financing, interest carry, fees, lease-up, insurance, taxes and reserves. The percentage soft-cost allowance must be replaced with a cost schedule, avoiding double counting.

  6. Land and assistance

    Use the RFP land price. A discount is not automatic: the RFP describes exceptions tied to additional affordability or substantial public benefit. If considering City assistance, price any associated wage, procurement and participation requirements before counting a net subsidy benefit.

  7. Evidence before commitment

    Obtain boundary/topographic survey, geotechnical and environmental information, utility capacities, comparable achieved rents/sales and at least two scoped contractor estimates. Neighboring heights are estimates; winter shadow checks are a design screen, not a certified daylight study.

  8. Buyer commissioning

    Study ownership separately with saleable rather than gross area, buyer deposits, construction finance, shared-court easements, legal subdivision, association reserves and completion guarantees. Distinct facade colors do not create independent legal buildings or financeable parcels.

Evidence and limits

Geometry was checked against saved floor allocations, not a new survey. Ground/upper door schedules, opening ownership, opening collisions, model triangulation, courtyard objects, source assumptions and scenario arithmetic were reviewed. Unit room relationships remain only partially encoded. The existing shadow study retains approximate neighboring heights. Historical drawings and the separate October 7 workbook are snapshots; they do not automatically inherit this revision.